Moranbah-Alpha Pipeline
Project Summary
The Moranbah to Alpha Pipeline project will deliver water to the Galilee basin to meet forecasted demand for water by commercial mining operations and provide a reliable water supply to the town of Alpha.
| Key milestones | |
|---|---|
| Preliminary design finalised | Completed |
| ECI Tender to market | October 2011 |
| RFT closes | December 2011 |
| ECI contractor selected | February 2012 |
| Award stage 2 contract | 2012 |
| Detailed design finalised | April 2012 |
| Permits and approvals gained | April 2012 |
| Commencement of construction | 2012 |
| Construction complete and pipeline operational | 2014 |